ICDAS ENERGY
Übernahmeort
Shanghai Port, China
Lieferort
Icdas Biga, Turkey

- Kunde
- ICDAS ENERGY
- Ladung
- ROTOR FOR 600 MW SUPER CRITICAL COALFIRED POWER PLANT
- Land
- TURKEY
- Versanddatum
- APRIL 2016
- Volumen
- 1 Unit // 71,250 mts // 58,42 cbm LxWxH : 12420 x 2100 x 2240 mm
Projektfotos

Projektumfang
- Acceptance of the Cargo at Shanghai Port / RoRo Terminal.
- Stuffing of Cargo onto Mafi.
- Lashing /Securing/Dunnage Cargo on Mafi.
- Loading the Mafi into RoRo vessel.
- Sea Transportation from Shanghai Port to Derince Port by RoRo Vessel.
- Discharging Mafi from RoRo Vessel.
- Unloading Cargo from Mafi and Re-loading onto Hydraulic Trailer.
- Lashing /Securing Cargo on Hydraulic Trailer.
- Arranging Transit Customs Declaration from Derince Port Customs to Biga Customs.
- On-carriage by Bonded Trailer from Derince Port to Icdas Factory in Biga with Road.
- Permission and Escort.