ALBA PROJECT MAYSUN
Place of receipt
Istanbul, Turkey
Place of delivery
Alba Jobsite, Bahrain

- Account
- ABB ELETRICS
- Cargo
- Transformer
- Country
- BAHRAIN
- Shipment date
- JANUARY 2017
- Volume
- 55 pckgs// 150 mts // 350 Cbm each LxWxH : 6200 x 3000 x 430 mm // 84000 KGs each
Project photos

Scope of project
- Pre Carriage from Factory to Port.
- Acceptance of the Cargo at Derince Port.
- Unloading of Cargo from Lowbed into Port Storage Area.
- Arranging Loading into Chartered Vessel.
- Arranging all Lashing/Dunnage/Securing of Cargo on Board.
- Sea Transportation ex Derince Port to Khalifa Bin Salman Port by Vessel.
- Discharging Cargo from Vessel at Khalifa Bin Salman Port.
- Arranging Custom Clearance.
- Arranging Transportation to JobSite ALBA.
- Discharging Cargo and Instatalion via Skid & Jacking method.